Policy Statement on Flood & Coastal Defence

1. Introduction

Purpose

1.1 This policy statement has been prepared by Torbay Council to provide a public statement of the Council's approach to flood and coastal defence in its area.

Background

1.2 The Department of Environment Food & Rural Affairs (DEFRA) has policy responsibility for flood and coastal defence in England. However, delivery is the responsibility of a number of flood and coastal defence "operating authorities" i.e. the Environment Agency, local authorities and internal drainage boards. Responsibilities differ according to the type of operating authority and Torbay Council's responsibilities are set out in paragraphs 3.1 and 3.2 below.
1.3 The Government has published a policy aim and three objectives for flood and coastal defence. To ensure a more certain delivery of the aim and objectives by the individual operating authorities the Government has published a series of high level targets. The first target requires each operating authority to publish a policy statement setting out their plans for delivering the Government's policy aim and objectives in their area. This will include their assessment of flooding and coastal erosion risk in their area, and the plans for reducing or managing that risk.
1.4 This policy statement fulfils that requirement. Copies are also available from Torbay Council's offices at the Civic Offices, Torquay, TQ1 3DR. We are also providing a copy to:
DEFRA and the Environment Agency.

2. How the Council will deliver the Government's Policy aim and objectives:

2.1 Torbay Council acknowledges and supports the Government's aim and objectives for flood and coastal defence (as set out below). Our policy and approach will be consistent with them, as follows:

Government's policy aim:

To reduce the risk to people and the developed and natural environment from flooding and coastal erosion by encouraging the provision of technically, environmentally and economically sound and sustainable defence measures. Section 3 below sets out our plans for reducing or managing the risk of flooding and coastal erosion risk in the Council's area.

Objective (a):

To encourage the provision of adequate and cost effective flood warning systems.
Provision of flood warning systems is the responsibility of the Environment Agency. However, Torbay Council recognises its related and important role in emergency planning and response. We will therefore:

Objective (b):

To encourage the provision of adequate, economically, technically and environmentally sound and sustainable flood and coastal defence measures.
Torbay Council will provide an adequate, economically, technically and environmentally sound approach to providing the flood and coastal defence service. We will:

Objective (c):

To discourage inappropriate development in areas at risk from flooding and coastal erosion.
As a local planning authority for our area, Torbay Council will take account of flooding and coastal erosion risks in all matters relating to development control, including development plans and individual planning applications, in accordance with Planning Policy Guidance Notes 20 and 25.

3. Our Assessment of the risk of flooding and coastal erosion in our area and what we will do to reduce or manage that risk:

Flood and coastal defence responsibilities:

3.1 Apart from certain obligations to protect internationally important habitats under the EU Habitats Directive, all flood and coastal defence works are undertaken under permissive powers. This means that operating authorities, such as Torbay Council, are not obliged to carry out flood and coastal defence works. It is also important to note that the Council does not normally accept responsibility for maintenance of flood defences on private land; this is the responsibility of the landowner.
3.2 Torbay Council is the relevant operating authority for:
3.3 The flood and coastal defences that are owned or managed by the Council are detailed in our return for the database which is maintained by the Environment Agency.
3.4 The Environment Agency is the relevant operating authority for flood defences on designated main rivers of which there is one in Torbay. Culverts under roads are generally the responsibility of Torbay Council.

Assessment of flood risk:

3.5 There are 42 km of ordinary watercourses for which Torbay Council is the relevant operating authority. These are all of the watercourses in the Council's area except Galmpton Watercourse (1.5 km) which is classified as a main river and hence the responsibility of the Environment Agency. There is no internal drainage board operating in the Council's area.
3.6 We have agreed with the Environment Agency that within the Council's area there are 19.2 km of "critical ordinary watercourses" (i.e. watercourses which are not classified as "main river" but which the Council has agreed with the Environment Agency to be critical because they have the potential to put at risk from flooding large numbers of people and property).
3.7 Based on historical flooding information, coupled with the Environment Agency's indicative flood plain maps, the Council has carried out an assessment of the risk of flooding from the ordinary watercourses in our area. The main areas at risk of flooding are Victoria Stream, Churston, Occombe Valley, Clennon Valley, Higher Brixham and Yalberton watercourses. The Council is satisfied that there are minimal risks to human life created by these flood risks from ordinary watercourses, but emphasises the need for the Environment Agency's flood warnings to be heeded, where these are provided (see below).

Action to reduce or manage flood risks:

3.8 The main means by which flood risks will be managed is through the Environment Agency's flood warning dissemination plan. This makes arrangements for warnings to be provided within this Council's area. Torbay Council has included plans for responding to both major and minor flooding in its emergency planning procedures and has arrangements for cascading warnings received from the Environment Agency to relevant Council services.
3.9 The Council has a programme in place to inspect the state of:
3.10 The Council will ensure that regular maintenance is carried out on the flood defences and channels which we own, or for which we accept responsibility, so that they operate at optimum efficiency. Where the responsibility for maintenance rests with a landowner, we will aim to secure co-operating in ensuring appropriate maintenance takes place, drawing on enforcement powers if necessary.
3.11 The Council's major capital work plan is to carry out flood alleviation works at Higher Brixham Watercourse during 2004/05 (DEFRA funding received) and subject to DEFRA funding being received flood alleviation works will be carried out on the Victoria Stream (Paignton town centre) during 2005/06. In addition to these flood alleviation schemes we are also proposing to carry out remedial works to Goodrington North seawall during 2006/07 subject to DEFRA funding.
3.12 By following Government guidance in Planning Policy Guidance Note 25 on development in flood risk areas, the Council, acting as a local planning authority, will ensure that risks are further minimised. This includes measures for ensuring sustainable urban drainage systems to control surface water run off.

Assessment of coastal erosion risks:

3.13 As identified in the 1998 Shoreline Management Plan, of the 36km of shoreline in the Council's area, 9km is defended against erosion. The remaining 27km frontage consists of natural undefended cliff.
3.14 Risks of erosion of the defended frontages are low. Elsewhere on the undefended coast, erosion rates average 0.2 metres per year (see 1998 SMP for details).

Action to reduce or manage coastal erosion risks:

3.15 The Council operates a programme of routine inspection and maintenance works to the protected frontage. On the undefended length warning notices are maintained in areas of potential danger on both cliff top and beach. Our management regime takes into account the most recent predictions of the impact of climate change as set out in the 1998 SMP.

4. Partnerships & Review of this Policy Statement

4.1 The Council has set out its policy and approach to flood and coastal defence. We recognise the need to work in partnership with central Government and other operating authorities. Our local population also has an important part to play, in recognising the vital importance of watercourses in controlling flood risk and the need to avoid blockages, whether by dumping rubbish or obstructing flows in other ways. We ask members of the public to let us know of any problems which might increase the risk of flooding or coastal erosion.
4.2 Torbay Council intend to review this policy statement in three years' time, when it will be revised and reissued as necessary. Meanwhile, the Council welcomes any comments on the approach and policies set out in this statement.

References

1 Strategy for Flood and Coastal Defence in England and Wales MAFF and Welsh Office September 1993
2 High Level Targets for Flood and Coastal Defence Operating Authorities and Elaboration of the Environment Agency's Flood Defence Supervisory Duty MAFF, November 1999
3 Lyme Bay and South Devon Shoreline Management Plan. June 1998




Contact Customer Services